If the actual level of activity is 4% less than planned, then the costs in the static budget should be reduced by 4% before comparing them to actual costs.

If the actual level of activity is 4% less than planned, then the costs in the static budget should be reduced by 4% before comparing them to actual costs. 




a. True
b. False



Answer: B