A labor efficiency variance resulting from the use of poor quality materials should be charged to: ACC302 A labor efficiency variance resulting from the use of poor quality materials should be charged to: A. the production manager. B. the purchasing agent. C. manufacturing overhead. D. the engineering department. Answer: B Learn More : Share this Share on FacebookTweet on TwitterPlus on Google+