A favorable materials price variance coupled with an unfavorable material usage variance would most likely result from:
A. labor efficiency problems.
B. machine efficiency problems.
C. the purchase and use of higher than standard quality material.
D. the purchase and use of lower than standard quality material.
Answer: D